Case Study
Temperature humidity and air quality control system for major UK joinery company
Overview
Client: Major UK Joinery Company
Industry: Construction
Project Overview: Penmann creates a controlled environment for a major new process.
Outcomes
- Conditioned environment at 26°C
- Absolute moisture levels between 12g/m³ and 5g/m³ all year round
- Area positively pressurised to prevent ingress of contamination
- System filtered to E12 HEPA EN1822 ( 99.5% efficiency )
- System installed to fit round new process
- Project delivered on time and budget
Challenges
The brief was to design a system to fit and operate around a new piece of key capital equipment and to understand the restrictions it could place on our design.
We were required to work seamlessly around other trades on a busy installation site.
Throughout the process we were called on to provide flexibility and understanding to adjust the design in real time and cater for changes by our client.
Solutions
- 17.6 m³/s Air handling unit
- Adiabatic humidifier to maintain moisture levels
- Trane CGAF 100 Chiller installed to provide cooling
- Air delivered using fabric socks engineered to fit around the new process
- System linked to onsite BMS system
Conclusion
This project successfully achieved a stable, conditioned environment at 26°C with moisture levels between 12g/m³ and 5g/m³, using a positively pressurized area and E12 HEPA filtration to prevent contamination. Our flexible approach enabled seamless integration of a 17.6 m³/s air handling unit, adiabatic humidifier, and Trane CGAF 100 Chiller, delivering air precisely through fabric socks around new process equipment. Despite the busy installation site and the need for real-time design adjustments, we completed the project on time and within budget, demonstrating our expertise and reliability in managing complex environmental control systems.