The Outcomes:
The Challenge:
KP Foods had an existing plant serving two packing halls with an area in excess of 13500m2 and a cooling load greater than 1MW.
The existing system, which utilised air sock distribution, was unable to meet cooling requirements and also proved difficult to maintain.
The Solution:
We redesigned the system to operate as a displacement system. The air handling plants were reduced by 50%, with any retained units being refurbished.
The sock air distribution system was replaced with floor-mounted displacement terminals. Some terminals were mounted above production equipment due to floor space restrictions.
The refrigeration was replaced with a new plant approximately one-third the size of the original.
The new system only requires a supply air temperature of 17°C to 26°C in the occupied space, enabling the use of free cooling for most of the year. It also has the added benefit of minimising the amount of recirculated room air.
We are very happy with the cooling tunnels designed and supplied by Penmann. All projects have been undertaken in an extremely efficient manner and have been delivered on time and on budget, and we have been particularly pleased with the performance of the tunnels.
Stephen Graves Factory Engineering Manager Muller Dairy
Penmann were able to offer a flexible approach to both design and contracting backed by excellent Health & Safety planning and implementation. We were more than happy with the professional manner with which they carried out the contract and would be only too pleased to recommend them to others.
Phil Griffiths, Engineering Manager McVities Manchester
We found Penmann to have an excellent understanding not only of air conditioning and refrigeration but also of the production process and the logistics that surround it. All timescales were achieved and the systems are working well. I would have no hesitation in recommending Penmann to others.
David Underdown, Sales Director, Rachels Dairy
All installation work was performed on time and to a high standard. The installation team, ensured that they worked safely and that the safety of others around the working area was considered at all times.
Michael Clifford, Engineering Manager Britvic Soft Drinks
Arla was pleased to engage the services of a locally based company on such a prestigious project. Penmann were able to work seamlessly with us to deliver a high quality product.
Tim Hutchinson, Project Manager Arla Foods Stourton
The service you provide through Penmann is always thorough, thoughtful and designed for a duty and service level that reflects the demanding 24/7/364 days operation we run here, and we therefore always call you first when manufacturing problems need specialised and bespoke HVAC solutions.
Robin Wright, Projects Manager, Bakkavor Desserts Newark